The old farm ground with villa was renovated for use as a training and conference center. Inside was installed a block-type thermal power station (max. 39 kW, cogeneration unit 1.200 kg and buffer storage tank 2.300 kg). The vibration insulation between the reinforced concrete floor (120 mm to 180 mm) and the existing solid ground floor was realized with HIGHMAT 30.

Problem.

The vibrations caused by the heating system caused disturbance in the training and conference center rooms.

Suggested solution.

The suggested solution using Highmat, a industrial derivation and prefabricated product, has minimized the disturbance thanks to its high performance. It is also very easy to install and don't required the help of specialized operators.

Result.

High acoustic insulation performance with reduced thickness, high acoustic comfort within the rooms, quick and easy to install.